Tenant Improvement Work

Construction at SL Green Realty Corp. is a simple structured process. Each step is accompanied with a letter clearly outlining the next steps, as well as the construction guidelines that your firm must follow.
 
The process is as follows:
  1. The tenant submits drawings for review to the following parties:
    • ​Property Manager: Endrit Kukaj
    • Chief Engineer: Eric Schweizer
    • Vice President of Construction: Roger Merriman
    • Reviewing Engineers for Comments:
      • MGE 
      • Severud (Structural)
  2. ​The Construction Administrator issues Letter 1, which outlines additional materials required:
    • Additional drawings (Architectural, Structural, HVAC, Electrical, Plumbing, Sprinkler, Fire Alarm)
    • General Contractors Insurance & Indemnification Agreement
    • Permit Expeditor assigned by SL Green to property: Brookbridge Consulting
      • The expeditor assigned by SL Green MUST be used unless stipulated otherwise in the lease.
  3. The reviewing engineer(s) & PM submit comments to VP. The comments are reviewed and Letter 2 is sent with said comments attached. Letter 2 must be signed and returned by the tenants.
  4. The tenant must resubmit drawings, conforming to the Reviewing Engineer's & PM's comments, to PM, CE & VP. If all comments are addressed and VP & PM have copies of Contractors Insurance & Indemnification Agreement as well as the appropriate permits, Letter 3 is issued, granting final approval. All subsequent coordination, scheduling, access, etc. must be arranged through the Property Manager.
  5. Project begins; SLG inspects construction site periodically.

Permit applications submitted by the building assigned expeditor for VP signature 
Note: For additional information please refer directly to your lease.